The following activities have been completed or have started in the four weeks.

  • The installation of temporary site power and plumbing.
  • The isolation of the existing small power, lighting and fire alarm cabling with the site demise.
  • The installation of internal wooden hoardings to segregate the building site from the church premises.
  • The installation of external hoardings and signage to close the footpath.
  • The strip out of the internal fixtures and fittings within the Park Road entrance lobby.
  • The demolition of non load bearing infill extensions.
  • The re-routing of existing fire alarm and small power cabling currently traversing through the work area, to enable further demolition activities.

Internal & External Hoardings

Site Office Internal Hoardings External Hoardings
Site Office  Internal Hoardings External Hoardings
 
 
 











 

Internal Strip Out

Internal Strip Out Internal Strip Out
Park Road Lobby Steps Park Road Lobby Ceiling
Flower Cupboard Internal Fixtures
Flower Cupboard Internal Fixtures & Finishes
 

Demolition of Non Load Bearing Extensions

Park Road Porch Proch Roof Tiles
Park Road Porch Porch Roof Tiles
Park Road Lobby Exterior Wall Park Road Boundary Wall
Park Road Lobby Exterior Wall Park Road Boundary Wall
22/10/2026